The Davis Center was designed by Susan T Rodriguez | Architecture & Design and Mitchell Giurgola Architects as part of larger re-envisioning of the site by the Central Park Conservancy's landscape ...
Project Update: Design is complete and permitting and legal review of the contract are in progress. The completion date has changed. To learn more about why schedules change, please visit the How We ...
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page. The average time for procurement is 9-12 months. The procurement timeline for this ...
Project Timeline Design. Assigned & Start Date: May 2023 Projected Completion Date: October 2024 Completion Date: February 2025 Procurement. Start Date: April 2025 Projected Completion Date: April ...
Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s ...
Project Update: Design is complete and permitting and legal review of the contract are in progress. The completion date has changed. To learn more about why schedules change, please visit the How We ...
About NYC Public Beaches. NYC Parks maintains 14 miles of beaches.Beaches are open from Memorial Day weekend through September 8, 2024. During beach season, lifeguards are on duty daily, from 10 a.m.
This project will reconstruct the Queens Storehouse in Flushing Meadows Corona Park. The work will include reconstructing portions of the roof, exterior walls, and floor slab; new screening, signage, ...
This project will reconstruct the basketball courts at Detective Keith L. Williams Park (Liberty Park). The completion date has changed. To learn more about why schedules change, please visit the How ...
Project Timeline Design. Assigned & Start Date: May 2023 Projected Completion Date: October 2024 Completion Date: November 2024 Procurement. The average time for procurement is 9-12 months. The ...
This project will reconstruct the track, synthetic turf field, tennis courts, and playground at Detective Keith L. Williams Park. The work includes new synthetic turf, new track, bleachers, tennis ...
Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration. The completion date has changed. To learn more about why schedules change, ...